Hi,

Is it possible to do three changes to Redmine?
  1. Allow a user with the correct security rights to change the start date and due date? Currently readonly after issue/feature created?
  2. When the user sets the start date, the due date automatically changes to the start date if due date smaller then start date. Rather fustrating when setting up a huge project with lots of features/issues and you keep having to scroll three, four months ahead.
  3. Also if a subtask is created it takes on the parent tasks start date.