How can I achieve these things regarding due dates with issues and versions.

Added by James Deeman over 13 years ago

Hi there, I hope this is an OK place to put this question as the 'Help' forum seemed to be specifically about getting help with Redmine itself. My question is a little bit more high level.

Basically i want to be able to configure the Redmine we use at work to do the following:

  1. Default the due date for Issues linked to Versions to the due date of the version.
  2. Hilight when Issue due dates are later than the due date of the Version it is linked to.
  3. Filter down an changes to Version due dates to the Issues that are linked too it.

Now I am pretty sure that number 3 is covered by the Better Gantt Chart plugin. I have also found the Issue Due Date plugin which should take care of number 1 but it hasn't been updated for a long time and I want to check if it will work with 1.2.x. I have no idea if the third one is possible.

Any help on this would be much appreciated.