Project

General

Profile

Actions

Defect #10990

open

Progress computation issue for versions with subtasks

Added by Evolis BE-Soft over 12 years ago. Updated over 12 years ago.

Status:
New
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:
Affected version:

Description

For a given version (says R1), I define a task A with two subtask A.1(2h) and A.2(8h).

When A.1 is done, the progress bar value is 10%
Then if A.2 is done, the progress bar value is 50%

I calculate the issue done ratio with the issue status and done = 100%
It appears that progress computation should not take care of parent estimated time.

Actions #1

Updated by Jean-Philippe Lang over 12 years ago

  • Subject changed from Progress computation issue to Progress computation issue for versions with subtasks
Actions

Also available in: Atom PDF