Feature #15886

open

Calculation of forecast dates between related tasks

Added by Leandro Gehlen almost 11 years ago. Updated about 9 years ago.

Status:
New
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:

Description

  • Add field working hours in Administration->Settings->Issue tracking

With this field you can calculate the starting date of the next issue related

  • Take into account the Estimated time field to calculate the date of the next task
  • Take into account the Non-working days field (Administration->Settings->Issue tracking) to calculate the date of the next task

Files

working_hours.png (31.9 KB) working_hours.png Leandro Gehlen, 2014-01-16 12:18
Actions #1

Updated by Toshi MARUYAMA almost 11 years ago

  • Tracker changed from Patch to Feature
Actions #2

Updated by @ go2null about 9 years ago

Estimated Time is more of the Effort, rather than the Duration and it is normally used for billing in Redmine.
Also, Redmine code refers to Duration separately.

Some PMP refs:
https://www.passionatepm.com/blog/effort-versus-duration-versus-elapsed-time-pmp-concept-16
http://www.pmbypm.com/difference-project-effort-and-duration/