Feature #14660
Updated by Toshi MARUYAMA over 11 years ago
Given there are three tickets, * task-A * task-B * task-C on a tracker named "tasks". Relations are set * task-A precedes task-B * task-B precedes task-C These are kind of processes that hand works to another. * We want to set "related to" relation between task-A and task-C, because the output of the task-A becomes input of task-C. * However, Redmine 2.2.2 and Redmine 2.3.2 does not allow us to do it, says "This relation would create a circular dependency". * Please reconsider excluding "related to" from circular dependency check. So far I am thinking that it will not cause contradiction. * Apparently, re-entering X-Y relation as Y-X is unnecessary and should be blocked.