Project

General

Profile

RedmineTimeTracking » History » Revision 13

Revision 12 (Etienne Massip, 2012-04-19 11:45) → Revision 13/19 (Mischa The Evil, 2012-04-19 14:16)

h1. Time tracking 

 {{>toc}} 

 h2. Introduction 

 Time tracking allows users to track how many hours of work are logged to a specific issue or project. Each time entry of "spent time" can be categorized by activity, and further explained with comments. By filling time estimates, project managers are able to produce better suited project planning as well as follow individual users progress.  

 Time tracking is always related to a user, thus it can be used to track how many billable hours this user has accomplished. See the [[RedmineTimelogDetails|spent-time details]] or [[RedmineTimelogReport|spent-time report]] pages for more information. 

 h2. Installing/Configuration 

 Time tracking is a standard module of Redmine and can be enabled/disabled for each project in the *Modules* section of the new project form, or the *Settings* tab of an existing project. 

 h2. Logging time on an issue 

 You can log time on an issue by clicking !/images/time_add.png! *Log time* from the issue details view. 

 p=. !log_time.png! 

 You can also log time when updating an issue. 

 p=. !Update_LogTime.png! 

 h2. Logging time at project level 

 You can log hours at project level by leaving the issue field empty. 

 h2. Accepted time formats 

 Estimated and spent hours can be entered using the following formats: 
 * Hours and minutes using standard time format: @1h@, @1 h@, @1 hour@, @2 hours@, @30m@, @30min@, @1h30@, @1h30m@, @1:30@ 
 * Hours and minutes using decimal time format: @1.5@, @1,5@ (equals to @1h30@) 

 h3. Decimal time format 

 When entering estimated- and spent-time values in Redmine using "decimal time format":http://en.wikipedia.org/wiki/Decimal_time you have to be aware of the following situation: 

 * _Example_: you have 4 issues with the following spent time values: 1.00, 0.10, 0.15, & 0.40. Now in the Spent-Time reports (Project overview -> Spent time -> [Details | Report]) you see a total of 1.65 hours instead of 2.05 hours...??? 

 * _Explanation_: this "behaviour" is normal and intended since you enter those four spent-time values using decimal time format. This means that:  
 ** 1.00 decimal equals 60 minutes (1 hour) 
 ** 0.10 decimal equals 6 minutes 
 ** 0.15 decimal equals 9 minutes 
 ** 0.40 decimal equals 24 minutes 
 ** 1.65 decimal equals 99 minutes 
 ** 2.05 hours (125 minutes) equals 2.0833333333333335 (est.) in decimal notation 

 Of course there can possibly be a very tiny difference (as you can see) due to the rounding to two decimals done by Redmine. 

 Some references: 
 * http://en.wikipedia.org/wiki/Decimal_time 
 * http://www.springfrog.com/converter/decimal-time.htm 

 

 h2. Logging time via commit messages 

 With the *Enable time logging* option turned on (see _Application settings -> Repositories_), developers developpers can log time against an issue via their commit messages using the following syntax (hours must be preceded with an issue id): 

   Fixed something, #435 @1h30 

 This commit message will log 1h30 on issue !#435.