Can't set parent task to existing issue

Added by Matej Kenda about 12 years ago

I created a few top-level tasks in a project. Later I realised that it would be better to have them as subtasks of another issue.

However, I am unable to set the parent task for these two tasks:

There is no "Parent task" field in the update form of the top level issue.

Is there a way to move top-level issues to become subtasks of another issue?

$ RAILS_ENV=production script/about

Environment:
  Redmine version                          2.1.2.stable
  Ruby version                             1.8.7 (x86_64-linux)
  Rails version                            3.2.8
  Environment                              production
  Database adapter                         MySQL
Redmine plugins:
  redmine_wktime                           1.1

Replies (1)

RE: Can't set parent task to existing issue - Added by Matej Kenda about 12 years ago

I found the solution almost immediately after posting the question:

  • Configuration for this tracker didn't have "Parent task" field enabled.