Defect #13092
closedBug On Start Date and Due Date
0%
Description
Hi,
This is production environnement :
-Redmine 1.3.0.stable.8319 (SQLServer)
-SQL SERVER 2008 r2
-Windows Server 2008 r2
I have a bug to display start date and due date. Look 2013-02-06_1552.png to see what happen.
If i update ticket, this is log file entry :
issue"=>{"start_date"=>"2013-02-08", "estimated_hours"=>"", "parent_issue_id"=>"", "priority_id"=>"3", "project_id"=>"22", "is_private"=>"0", "lock_version"=>"0", "done_ratio"=>"0", "assigned_to_id"=>"16", "subject"=>"TEST DATEa", "tracker_id"=>"4", "due_date"=>"2013-02-14", "status_id"=>"1", "description"=>"azeazeazeazeaze\r\naze\r\naz\r\neaz\r\neaz\r\ne\r\naze"}, "controller"=>"issues", "attachments"=>{"1"=>{"description"=>""}}}
But Redmine display
due date : 01/02/2013.
It's like a cut the date.
In my Database, i have the correct entry : Look 2013-02-06_1558.png
I try to update my developpement production to :
-Redmine 1.4.4.stable
-SQL SERVER 2008 r2
-Windows Server 2008 r2
I had the same error.
Can you help me please ?
Thank you very much