Feature #13694
openextend information overlays for issues that are shown on gantt chart
Status:
New
Priority:
Normal
Assignee:
-
Category:
Gantt
Target version:
-
Start date:
Due date:
% Done:
0%
Estimated time:
Resolution:
Description
When viewing the gantt charts the planned begin and end dates are shown as a bar and the overlay shows some information about the task as mousOver effect.
One information that is really important in this view is the time in hours that was estimated for an issue.
Maybe you can add the "estimated time" to this overlay?
Updated by Ka. Pa. almost 11 years ago
For my project, I need to show category information.
So it will be very usefull if we can choose which information we want to be shown on the gantt screen to please everybody.