Description
The gantt charts cannot be updated automatically according to the changes of the issues.
Environment:
ruby 1.8.6 (2007-09-23 patchlevel 110) [i686-linux]
Rails 2.0.2
Redmine 0.6.devel.105
Reproduce:
1. In a project, close an issue.
2. Go to the gantt chart view.
3. The chart is not updated to represent the change. (The issue still in the open status)
Note:
It work fine after the caching is disabled.
Related issues
History
#1
Updated by Alex Aktion over 14 years ago
Strange, Gantt view is different when i selecting Tracker or/and
months to show. I'v sent screenshots to admin.
#2
Updated by Alex Aktion over 14 years ago
Update: Its either deferred update or i just selected Apply button
on right side of Gatt menu and its actual now
#3
Updated by Alex Aktion over 14 years ago
Yes, have almost same problem here.
Added new milestone and moved some old tasks to new milestone
and Gantt still show old situation and even don't show new
milestone!
#4
Updated by Jean-Philippe Lang over 14 years ago
- Status changed from New to Closed
- Resolution set to Fixed
Fixed in r1157.