Description

When changing the date of a version, the roadmap shows the change correctly, but when you look at the calendar it shows the old date and the new date. In other words, I create a version (lets say beta 1) with the date of Feb 2, 2008. I then change the date of beta 1 to March 4, 2008. The calendar will show Beta 1 on both Feb 2 and March 4. The roadmap tab shows Beta 1 on March 4, 2008


Related issues

Related to Redmine - Defect #185: Gantt chart cannot be updated automatically Closed

History

#1 Updated by Jean-Philippe Lang over 14 years ago

  • Status changed from New to 7
  • Assignee set to Jean-Philippe Lang

Gantt and calendar use fragment caching which is not properly expired when editing issues or versions.
I think I'm gonna disable this cache.

#2 Updated by Jean-Philippe Lang over 14 years ago

  • Status changed from 7 to Closed
  • Resolution set to Fixed

Fixed in r1157.