Defect #21449
openAutomatic done ratio calculation in issue tree is wrong when parent has its own estimated time
Status:
New
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
Due date:
% Done:
0%
Estimated time:
Resolution:
Affected version:
Description
Due to the change in r14272 estimated_hours are now independent for parent and subtasks. But, it seems that automatic calculation of done ratio is still based on estimated time of children, ignoring value provided for the parent.
e.g.
- A (2h)
- B (2h)
- C (2h) 50% done
- B (2h)
This results with 50% done ratio on all tasks up to A, what, from estimated time point of view, is wrong - only 1 of 6 hours is "done".
I do not see a fix for this when automatic done ratio calculation is enabled as there is no way to say that some work on parent has been also done. Anyway, latest changes leads to inconsistency