Feature #6167
Add option to weight parent task %-done based on the estimated time
Status: | Closed | Start date: | 2010-08-18 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | - | % Done: | 100% | |
Category: | Issues | |||
Target version: | - | |||
Resolution: |
Description
Calculation of parent's percentage depends on number of subtasks, not amount of days (hours). For example if your parent is of two subtasks, one of 1 month, 100% done, second is one day, 0% done, the parent will be calculated 50% done, which is strange, since second subtask is a tiny bit. I think calculation based on number of hours is more representative.
Related issues
History
#1
Updated by Moritz Voss over 11 years ago
+1 absolutely. This should be an option - if an hour estimate exists, include an option to weigh tasks according to this, preferrably per-tracker. (we have Plan, Issue and Porting trackers, only the plan has long items, where in the other two, the number of items counts).
#2
Updated by Mischa The Evil over 11 years ago
- Tracker changed from Defect to Feature
- Subject changed from Parent task percentage wrong to Add option to weight parent task %-done based on the estimated time
#3
Updated by Bruno Medeiros about 11 years ago
- Status changed from New to Resolved
- % Done changed from 0 to 100
Don't know since when, but it's already this way. See:
http://demo.redmine.org/issues/4334
Two childs:
c1 with 10 hours, 100% complete.
c2 with 20 hours, 0% complete.
parent completion is at 33%, correct.
#4
Updated by Jan Niggemann (redmine.org team member) over 9 years ago
Closing this, status is resolved since 400 days and more (issue was last updated more than 400 days ago)...
#5
Updated by Jan Niggemann (redmine.org team member) over 9 years ago
- Status changed from Resolved to Closed