Feature #6167
closedAdd option to weight parent task %-done based on the estimated time
100%
Description
Calculation of parent's percentage depends on number of subtasks, not amount of days (hours). For example if your parent is of two subtasks, one of 1 month, 100% done, second is one day, 0% done, the parent will be calculated 50% done, which is strange, since second subtask is a tiny bit. I think calculation based on number of hours is more representative.
Related issues
Updated by Moritz Voss about 14 years ago
+1 absolutely. This should be an option - if an hour estimate exists, include an option to weigh tasks according to this, preferrably per-tracker. (we have Plan, Issue and Porting trackers, only the plan has long items, where in the other two, the number of items counts).
Updated by Mischa The Evil almost 14 years ago
- Tracker changed from Defect to Feature
- Subject changed from Parent task percentage wrong to Add option to weight parent task %-done based on the estimated time
Updated by Bruno Medeiros over 13 years ago
- Status changed from New to Resolved
- % Done changed from 0 to 100
Don't know since when, but it's already this way. See:
http://demo.redmine.org/issues/4334
Two childs:
c1 with 10 hours, 100% complete.
c2 with 20 hours, 0% complete.
parent completion is at 33%, correct.
Updated by Jan Niggemann (redmine.org team member) almost 12 years ago
Closing this, status is resolved since 400 days and more (issue was last updated more than 400 days ago)...
Updated by Jan Niggemann (redmine.org team member) almost 12 years ago
- Status changed from Resolved to Closed