Defect #7515
closedRoadmap Version Time Tracking Error
Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Roadmap
Target version:
-
Start date:
2011-02-01
Due date:
% Done:
0%
Estimated time:
Resolution:
Duplicate
Affected version:
Description
When viewing parent tasks (with subtasks), the estimated & spent hours reflected are those of the subtasks, which is what I would expect.
However, when I attach the parent task to a version (and only the parent task), the estimated & spent hours are 0, though the subtasks have time estimates and spent time.
For consistency, I believe the estimated & spent hours for the version, should reflect the totals for all tasks/subtasks.
Related issues