Feature #9413
openSoft start and due dates of an issue
Status:
New
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
2011-10-13
Due date:
% Done:
0%
Estimated time:
Resolution:
Description
Now, start and due dates of an issue are hard. It doesn't allow to reschedule its project based on dependencies and durations.
I suggest to take the dates as soft ones (to allow their reschedule) unless checkboxs at field Start date and/or Due date are checked.
Sorry if I submitted a duplicated issue. It is very hard to search in those 2.000+ feature requests.
       Updated by Etienne Massip about 14 years ago
      Updated by Etienne Massip about 14 years ago
      
    
    - Category changed from Projects to Issues
       Updated by Etienne Massip about 14 years ago
      Updated by Etienne Massip about 14 years ago
      
    
    Did you know that dates were actually modified depending upon issue relations (see RedmineIssues)?