Feature #9415
openMore fine dependencies between issues
Status:
New
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
2011-10-13
Due date:
% Done:
0%
Estimated time:
Resolution:
Description
Now, only dependecies "precedes" and "follows" exists to order 2 issues time schedule.
I suggest to add more dependencies according project management:
- FS: end A - start B
- SS: start A - start B
- FF: end A - end B
- SF: start A - end B
See eg. http://en.wikipedia.org/wiki/Dependency_(project_management) for a detailed description.
It would allow reschedule of start and due dates of issues base on the dependencies and durations.
Sorry if I submitted a duplicated issue. It is very hard to search in those 2.000+ feature requests.