Project information
Added by Luiz Santos about 11 years ago
Hello, I'm new at Redmine, so sorry if I ask a stupid question, but...
It seems to me that the project does not have the information of who created the project, and where I work this is kinda of important. Is there a way to automatically append this information ( not by creating a custom field, because it does not allow default values for users ) to the project's information and display it using the webGUI?
Replies (8)
RE: Project information - Added by Ivan Cenov about 11 years ago
I looked at the database table 'projects'. It does not have a column 'created_by', 'author' or something similar. It seems that Redmine does not record information about who created which project. One solution is creating dedicated plugin for that.
RE: Project information - Added by Luiz Santos about 11 years ago
Is there any plugin already done that does something similar to it?
RE: Project information - Added by Alex Beresten about 11 years ago
Hello! Could somebody explain, what does RED line on Gantt's chart mean?)Thanks)
RE: Project information - Added by Ivan Cenov about 11 years ago
Alex Beresten wrote:
Hello! Could somebody explain, what does RED line on Gantt's chart mean?)Thanks)
The vertical line that is inclined left or right? It shows relative progress on issues.
RE: Project information - Added by Ivan Cenov about 11 years ago
Luiz Santos wrote:
Is there any plugin already done that does something similar to it?
I haven't seen such plugin.
RE: Project information - Added by Alex Beresten about 11 years ago
I mean horizontal red line on the task. Task line could be red and green. Why task line could be red? I append a picture to the post, example of red line is in the orange frame (week 36).Thanks!
Gant Chart.png (125 KB) Gant Chart.png |
RE: Project information - Added by Ivan Cenov about 11 years ago
Alex Beresten wrote:
I mean horizontal red line on the task. Task line could be red and green. Why task line could be red? I append a picture to the post, example of red line is in the orange frame (week 36).Thanks!
This shows how much of an issue is fulfilled. (10%, 20% .... 90%, 100%)
RE: Project information - Added by Alex Beresten about 11 years ago
So.. We have vertical dotted line which means current date (see attached pictire).
Tasks which are situated RIGHT to this line: planned time of implementing is GREY, implemented time is GREEN. Yes?
Tasks which are situated LEFT to this line: planned time of implementing is RED, implemented time is GREEN. Yes? These task are overdued as I understand. Thanks!
Gant Chart.png (125 KB) Gant Chart.png |