Project

General

Profile

Gantt chart error

Added by 查吾喜 查先生 about 6 years ago

Version 3.3.2
After the scheduled completion time is set in the task, the following error occurs when finding the Gantt chart.

Internal error
An error occurred on the page you were trying to access.
If you continue to experience problems please contact your Redmine administrator for assistance.
If you are the Redmine administrator, check your log files for details about the error.
Back


Replies (2)

RE: Gantt chart error - Added by Go MAEDA about 6 years ago

查吾喜 查先生 wrote:

After the scheduled completion time is set in the task, the following error occurs when finding the Gantt chart.

Does "scheduled completion time" mean "Due date" or "计划完成日期"? Can you see any errors regarding the problem in the production.log? Someone may be able to help you if you post more detailed information. Please see Submissions.

RE: Gantt chart error - Added by 查吾喜 查先生 about 6 years ago

resolved
Gantt Extension plugin Problems

    (1-2/2)