Added by Michael Diederich over 15 years ago
Hi,
I used the search and tryed myself, but I need your help!
I have a working package, which is calculated with xx working days. I can break it down into 5 pieces, each depending on the other. I have no due date for this project. I want to add all calculated working days and redmine should say me: If you start on 1st June, your whole development team can finish this project on 15th june in the following order of this gantt diagramm.
My problems are:
- Without due date, I cannot see it in the gantt diagramm
- My estiamted working time does not effect the due date
- The relations with "blocked by" are only effecting the first and the second ticket, not the 3rd and following tickets..
Thanks for any help,
da didi
Replies (4)
RE: Issues Relationship - Added by Brad Beattie over 15 years ago
My plugin, Schedules, can do this. You tell it how many hours each day each of your team members is working and it will calculate start and due dates for issues (and the end date for the version too).
RE: Issues Relationship - Added by Michael Diederich over 15 years ago
Brad Beattie wrote:
My plugin, Schedules, can do this. You tell it how many hours each day each of your team members is working and it will calculate start and due dates for issues (and the end date for the version too).
Thanks for your reply!
We already have your plugin in place, have set the next weeks our working times and free days, but I still search for the "calculate now" button ;) What are the requirements for the calculation? We do not have any versions in place, just some tickets with start daten, estimate hours and due dates..
Thanks!
RE: Issues Relationship - Added by Brad Beattie over 15 years ago
You need to create a version. When you do, a button on the version view page will appear called "Estimate".
RE: Issues Relationship - Added by jayaseelan karuppannan about 14 years ago
Michael Diederich wrote:
Brad Beattie wrote:
My plugin, Schedules, can do this. You tell it how many hours each day each of your team members is working and it will calculate start and due dates for issues (and the end date for the version too).
Thanks for your reply!
We already have your plugin in place, have set the next weeks our working times and free days, but I still search for the "calculate now" button ;) What are the requirements for the calculation? We do not have any versions in place, just some tickets with start daten, estimate hours and due dates..
Thanks!
Hi Brad,
I tried schedule plugin for redmine 0.9.0 But it is not working, please refer plugin which i am refering to.
http://blog.goyello.com/2009/10/14/redmine-schedule-plugin-a-precise-tool-for-resource-management/
could you please help us out.