Date time in ISSUES

Added by Fabio Hofer almost 13 years ago

Hi,
My question refer to the ISSUES functionality of Redmine.
Is it possible to change the fields START and DUE DATE within ISSUES from a date field to a date-time field?

Also, is it possible to automatically populate DUE DATE based on START and PRIORITY?
For example:
If : START = 01-NOV-2011 11:00am
and : PRIORITY = IMMEDIATE (max resolution time = 2 hours)
then: DUE DATE = 01-NOV-2011 13:00pm

In our project developers have deadlines to resolve issues, which can vary from 2 hours (immediate) up to 5 business days (low).

Thanks.


Replies (1)

RE: Date time in ISSUES - Added by Mischa The Evil almost 13 years ago

Both is not possible with a vanilla Redmine.