Subtasks on different projects.
Added by Jerome Castang almost 12 years ago
Hello all,
I try to set relationship between two tasks as "subtask" that are not on the same Project (or subprojects).
According http://www.redmine.org/issues/5487 it seems to be possible and configurable.
I am under redmine 2.1.4.
Can anyone help me ?
Replies (1)
RE: Subtasks on different projects.
-
Added by Mischa The Evil almost 12 years ago
Jerome Castang wrote:
I try to set relationship between two tasks as "subtask" that are not on the same Project (or subprojects).
According http://www.redmine.org/issues/5487 it seems to be possible and configurable.I am under redmine 2.1.4.
This feature has been implemented through #5487 in Redmine 2.2.0, and since you're on 2.1.4 I can only suggest to update your Redmine instance.