I noticed that the roadmap view for issues counts the parent issue time as well as the child issue time when it calculates the percent done. By calculating the parent issue it makes the percent done off.
Example:
I have a parent issue that has five children each being 1 hour (5 hours total). Instead of each child being worth 20% of the percent done they are only worth 10% because the parent issue is being counted as 50% (5 hours).
Fix:
Tell the query to ignore parent issues.