Defect #14815
time estimate should affect due date for gantt charts
Status: | Closed | Start date: | ||
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | - | % Done: | 0% | |
Category: | Gantt | |||
Target version: | - | |||
Resolution: | Duplicate | Affected version: | 2.3.2 |
Description
Two problems that make gantt charts quite useless in our case:
1. The Gantt chart does not appear to use issue duration to establish the task's end date.
2. The tasks appear in sequence if I add relationships but the Gantt durations is always one day.
Reported long time ago on board, but I failed to find such issue:
http://www.redmine.org/boards/2/topics/31769
Related issues
History
#1
Updated by Oscar Corsvall over 8 years ago
I agree this would be really good fix!
#2
Updated by Toshi MARUYAMA about 7 years ago
- Related to Feature #20323: Enhancement of gantt chart - consider estimated effort if no due date is set added
#3
Updated by Toshi MARUYAMA about 7 years ago
- Related to deleted (Feature #20323: Enhancement of gantt chart - consider estimated effort if no due date is set)
#4
Updated by Toshi MARUYAMA about 7 years ago
- Status changed from New to Closed
- Resolution set to Duplicate
I close this issue because #20323 has more description.
#5
Updated by Toshi MARUYAMA about 7 years ago
- Duplicates Feature #20323: Enhancement of gantt chart - consider estimated effort if no due date is set added