Defect #14815

time estimate should affect due date for gantt charts

Added by Peter Volkov almost 7 years ago. Updated almost 5 years ago.

Status:ClosedStart date:
Priority:NormalDue date:
Assignee:-% Done:

0%

Category:Gantt
Target version:-
Resolution:Duplicate Affected version:2.3.2

Description

Two problems that make gantt charts quite useless in our case:

1. The Gantt chart does not appear to use issue duration to establish the task's end date.
2. The tasks appear in sequence if I add relationships but the Gantt durations is always one day.

Reported long time ago on board, but I failed to find such issue:
http://www.redmine.org/boards/2/topics/31769


Related issues

Duplicates Redmine - Feature #20323: Enhancement of gantt chart - consider estimated effort if... New

History

#1 Updated by Oscar Corsvall over 6 years ago

I agree this would be really good fix!

#2 Updated by Toshi MARUYAMA almost 5 years ago

  • Related to Feature #20323: Enhancement of gantt chart - consider estimated effort if no due date is set added

#3 Updated by Toshi MARUYAMA almost 5 years ago

  • Related to deleted (Feature #20323: Enhancement of gantt chart - consider estimated effort if no due date is set)

#4 Updated by Toshi MARUYAMA almost 5 years ago

  • Status changed from New to Closed
  • Resolution set to Duplicate

I close this issue because #20323 has more description.

#5 Updated by Toshi MARUYAMA almost 5 years ago

  • Duplicates Feature #20323: Enhancement of gantt chart - consider estimated effort if no due date is set added