Description
Admin -> Settings -> Issue Tracking:
Calculate the issue done ratio with => 'Use the issue status'
Parent tasks attributes : % Done => Calculated from subtasks
If I set NEW is 0%, CLOSED is 100%.
When all subtasks are closed, the parent issue still is 0% (status is NEW).
But I hope it be 100%.
Can you add a switch? Force calculate the parent done ratio from subtasks?
Related issues
Updated by Toshi MARUYAMA over 8 years ago
- Subject changed from Calculate parent Issue's done ratio from subtasks to Calculate parent Issue's done ratio from subtasks in case of 'Use the issue status'
Updated by Go MAEDA over 8 years ago
- Is duplicate of Defect #6609: % Done for Parent Tasks [2] added
Updated by Go MAEDA over 8 years ago
- Status changed from New to Closed
- Resolution set to Duplicate
I am closing this issue as a duplicate of #6609.
Thank you for submitting this issue.