Description
If you have following situation, parent issue with relation to start n days after some other issue,
and try to add sub-issue, it will populate start date with today's date.
Instead, it should populate start date with calculated date, because any date entered before
calculated date would result with following error message:
Issue start date cannot be earlier than (actual calculated date) because of preceding issues