Defect #4454

closed

Related issues - blocks

Added by ga work over 14 years ago. Updated over 14 years ago.

Status:
Closed
Priority:
High
Category:
Documentation
Target version:
-
Start date:
2009-12-20
Due date:
% Done:

0%

Estimated time:
Resolution:
Invalid
Affected version:

Description

Hello Mischa,

I'm a new user with difficulty relating issues. I created an issue t1(start 22 - end 23) and added the relation "blocks" issue t2(start 22 - end 24) in the most recent test2 project in the demo. The % done is 0 is both cases. I haven't understood how this feature works. I've attached a snapshot of the calendar. Shouldn't the start date of t2 get pushed to the 23rd or the 24th? Also, is the difference between "blocks" and "precedes" just the ability to add delay?

Thanks in advance!

Tanya


Files

blocks.bmp (61.8 KB) blocks.bmp ga work, 2009-12-20 15:40