Feature #6127
closedPreceeded by / followed by - Same day
0%
Description
The current validation for issues that are linked by preceeded by / followed by issue links is that the start date of the latter cannot be the same as the finish date of the former.
For example this is not possible (Issue B follows Issue A)
Issue A - 2010/01/01 to 2010/01/10
Issue B - 2010/01/10 to 2010/01/20
The following issue must always start on the next day.
This seems rather arbitrary and annoying since we have tasks that may finish mid-day and wish to start on the next days in the afternoon.
For maximum flexibility I would suggest that the validation allows for following task to start on the same day as the last day of the preceding task.
Related issues
Updated by Mischa The Evil over 14 years ago
- Tracker changed from Defect to Feature
- Status changed from New to Closed
- Resolution set to Duplicate
Closed as a duplicate of issue #5655 (which also includes a hack for the thing).