Defect #7119
Missing done % for parent task with all 100% subtasks
Status: | Closed | Start date: | 2010-12-16 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | - | % Done: | 0% | |
Category: | - | |||
Target version: | - | |||
Resolution: | Invalid | Affected version: | 1.0.2 |
Description
I found that several tasks has problem with done % for parent tasks when all of subtasks are done on 100%
Redmine 1.0.2
mysql version: 5.1.30
ruby 1.8.7
Maybe this bug is similar with http://www.redmine.org/issues/6609 but I don`t sure.
History
#1
Updated by Mischa The Evil over 11 years ago
Have you configured your Redmine to calculate the issue done ratio using the issue status?
#2
Updated by Mikhail Tcishewsky over 11 years ago
This problem is solved.
Some guys using Mylyn Connector for eclipse and this plugin set "Estimated time" to 0 hours.
#3
Updated by Daniel Felix over 9 years ago
- Status changed from New to Closed
- Resolution set to Invalid
Mikhail Tcishewsky wrote:
This problem is solved.
Some guys using Mylyn Connector for eclipse and this plugin set "Estimated time" to 0 hours.
Due to this answer, I'm closing this old ticket.