Defect #8742
closed% done in parent task is incorrect
0%
Description
Hi,
I've created a parent task with 3 sub-tasks. All the sub-tasks have been closed with 100% but the % done in parent task is showing only 67% which is supposed to be 100%.
How can i rectify this problem as it affects my overall roadmap performance? Thanks
Files
Updated by Etienne Massip over 13 years ago
Any plugins that could explain this ?
What is the estimated time of each subtask ?
Updated by Etienne Massip over 13 years ago
- Category changed from Roadmap to Issues planning
Updated by Wendy Wong over 13 years ago
Etienne Massip wrote:
Any plugins that could explain this ?
What is the estimated time of each subtask ?
----------------------------------------------
~~ No plugins are being used
~~ No estimated time defined for each subtask, only due dates are defined
Updated by Etienne Massip over 13 years ago
What are the start and due dates of each task, please ?
Updated by Wendy Wong over 13 years ago
Etienne Massip wrote:
What are the start and due dates of each task, please ?
Parent task
-----------
13 Apr 2011 - 8 Jun 2011
Sub tasks
----------
1. 16 Apr 2011 - 6 May 2011
2. 15 Apr 2011 - 15 May 2011
3. 10 May 2011 - 8 June 2011
Updated by Anonymous almost 7 years ago
Wasn't able to reproduce.
With each completed child issue the parent issue's % done grew by 1/3, so it's been changing as expected: 33-66-100%.
Updated by Guillermo ML almost 7 years ago
Alexander Oleynikov wrote:
Wasn't able to reproduce.
The issue is 6 years old, I suppose it was solved some time ago. It works flawlessly on our 3.4.4 version.
Updated by Go MAEDA almost 6 years ago
- Status changed from New to Closed
- Priority changed from High to Normal
- Resolution set to Cant reproduce
I am closing this issue. Please open a new issue if you encounter the same problem again.