Gantt chart task durations

Added by Peter Roberts about 9 years ago

I am using Redmine 1.3.2 with redmine_better_gantt_charts
I have left the task due date blank.
The Gantt chart does not appear to use issue duration to establish the task's end date.
The tasks appear in sequence if I add relationships but the Gantt durations is always one day.

Is there a way of configuring the tool to show calculated duration on the Gantt or do I have to caluclate the due date and enter?
Happy to use another plugin.

Replies (4)

RE: Gantt chart task durations - Added by Mathias Schreiber about 9 years ago

Same problem with Redmine 2.0.3 without ANY plugins.
It looks as if Redmine does not use the estimated time when calculating the gantt.

Any advise?

RE: Gantt chart task durations - Added by Jan Niggemann (redmine.org team member) about 9 years ago

Has someone already posted a feature request for this?

RE: Gantt chart task durations - Added by Ben Moudry almost 8 years ago

Has anyone responded to this? I would like the Gantt chart to update based on estimated time so I can more accurately guestimate the completion time for a project.

RE: Gantt chart task durations - Added by Toshi MARUYAMA almost 6 years ago

FTR: #14815 and #20323