Parent task is invalid
Added by Paul Stamey over 11 years ago
I am receiving this message after I assign more than one task to a specific task.
Example
Parent Task 239 to 72
Attach Issue 240 to 72 receive Parent task is invalid when saving.
Replies (6)
RE: Parent task is invalid
-
Added by Martin Denizet (redmine.org team member) over 11 years ago
Are both Issues in the same project?
RE: Parent task is invalid
-
Added by Paul Stamey over 11 years ago
Yes both issues are part of a same project within a project.
Project 100
Project 120
Issue 100
Issue 102
RE: Parent task is invalid
-
Added by Paul Stamey over 11 years ago
Project 100
Project 120
Issue 100
Issue 102
RE: Parent task is invalid
-
Added by Mischa The Evil over 11 years ago
And you are trying to make issue 100 parent (or child, doesn't matter in this case) of issue 102?
Also (1) check for any issue relations between the issues, and (2) monitor your logs to see if they can provide more info about why this is happening.
RE: Parent task is invalid
-
Added by Pierre Pretorius about 11 years ago
Perhaps you are experiencing #13654.
RE: Parent task is invalid
-
Added by Jeff Pierson almost 11 years ago
To add to what Pierre is suggesting, I would check to see if the relationship is one of the "copied" relationships because this appears to have been giving me the same issue. I would assume that some relationships such as whether a bug was copied from another should not play into detecting cyclical relationships when assigning a parent/sub tasks but it appears that this may be what is happening at least in Redmine v2.3.1.