Unable to update an issue.
Added by Craig Beaumont over 15 years ago
Hi there,
I wonder if anyone can assist me?
We have been using RedMine for a while now - and I have been unable to change the status of logged issues, the option is grayed-out.
Please see the attached screen shot.
Thanks,
Craig.
redmine.jpg (23.7 KB) redmine.jpg |
Replies (5)
RE: Unable to update an issue. - Added by Nanda P over 15 years ago
Hi Craig,
Make sure you are a member of that project. To change the status, you should be a member (even if you are an administrator)
Check this issue : http://www.redmine.org/issues/2323
HTH..
Nanda
RE: Unable to update an issue. - Added by Craig Beaumont over 15 years ago
Hi Nanda,
I had a look - I am a member of the project in the capacity as a 'Developer Owner'.
But, still I cannot change the status of any task.
The tasks do have time logged with each, and the ones that I want to close's percentage is set to 100%.
Please see the attached JPG file.
Thanks for taking your time to reply,
Craig.
redmine.jpg (43.4 KB) redmine.jpg |
RE: Unable to update an issue. - Added by Craig Beaumont over 15 years ago
Here is a screen shot of the settings for a 'Project worker'.
Regards,
Craig.
redmine.jpg (139 KB) redmine.jpg |
RE: Unable to update an issue. - Added by Nanda P over 15 years ago
Check your work flow for the role "Developer Owner" & the Tracker "Maintenance"
You are the "Developer Owner" for the project, so please check the settings for "Developer Owner" not "project worker"
I don't think the percentage done is stopping you to change the status.
Can you able to change the status if you go to the task in Edit mode?
RE: Unable to update an issue. - Added by Craig Beaumont over 15 years ago
Ah ha!
Excellent, I see that the configuration did not allot a Developer to change the status :)
Nanda, thanks for your assistance, I greatly appreciated it!