I have 2 issues.
I set Issue 002 follows Issue 001. Issue 001's end date is Sept 1st.
If I change the end date of Issue 001 to 5 days later (to Sept 6th), I see Issue 002's start and end date aslo move forward (later) 5 days, which is good.
Here is the problem: if I move the end date of Issue 001 to 5 days earlier (to August 25th), the Start date and end date of Issue 002 does not move accordingly, instead, they just stay where they were - no changes. Why is that? How to fix it?
Thanks!
Related issues
Updated by john zhel over 12 years ago
Just to clarify: "I have 2 issues." in my previous post means I created 2 new issues in my Redmine to test out the related issue feature (one follows the other).
Updated by john zhel over 12 years ago
Found a solution here:
http://www.redmine.org/plugins/redmine_better_gantt_chart
where it says "•Fixed rescheduling of related tasks if due date of dependent task changed to an earlier date."
Just wondering, if there is a special reason the core makes it this way? Any idea?
Updated by Jean-Philippe Lang over 12 years ago
- Status changed from New to Closed
- Resolution set to Duplicate
No particular reason, it's just not implemented.