Start date of 2nd issue does not follow if the first issue end date moves up

Added by john zhel over 12 years ago. Updated over 12 years ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:
Duplicate
Affected version:

Description

I have 2 issues.

I set Issue 002 follows Issue 001. Issue 001's end date is Sept 1st.

If I change the end date of Issue 001 to 5 days later (to Sept 6th), I see Issue 002's start and end date aslo move forward (later) 5 days, which is good.

Here is the problem: if I move the end date of Issue 001 to 5 days earlier (to August 25th), the Start date and end date of Issue 002 does not move accordingly, instead, they just stay where they were - no changes. Why is that? How to fix it?

Thanks!


Related issues

Is duplicate of Redmine - Defect #8936: rescheduling of an issue to an earlier date does not update issues that follow on this issueClosed2011-07-28