Defect #11549
closedStart date of 2nd issue does not follow if the first issue end date moves up
Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
Due date:
% Done:
0%
Estimated time:
Resolution:
Duplicate
Affected version:
Description
I have 2 issues.
I set Issue 002 follows Issue 001. Issue 001's end date is Sept 1st.
If I change the end date of Issue 001 to 5 days later (to Sept 6th), I see Issue 002's start and end date aslo move forward (later) 5 days, which is good.
Here is the problem: if I move the end date of Issue 001 to 5 days earlier (to August 25th), the Start date and end date of Issue 002 does not move accordingly, instead, they just stay where they were - no changes. Why is that? How to fix it?
Thanks!