Feature #12816
openFilter issues by progress state
0%
Description
Hi there,
it would be really great (in addition to #12122), to filter the issue list by progress state.
Such a filter could be something like this:
Ticket A starts on 1.1.2013 and has the 4.1.2013 as due date. This means we would have 4 days for this ticket. If the current date is the 3.1.2013, we should have already 75% solved of this ticket. If the current done ratio is below this calculated value, this ticket is behind the progress state. If it is above this value, we are in front of the progress line.
This calculation should respect the configurable non-working days.
In this example we have the 1.1.2013 as star and the 7.1.2013 as due date. Our non-working days are saturday and sunday. this means we have 7-2 working days (5).
This would be helpful for the project manager to see which tasks are behind the estimated progress state. What do you think about it?
Best regards,
Daniel