Defect #14798

closed

Wrong done_ratio calculation for parent with subtask having estimated_hours=0

Added by Daniel Felix about 11 years ago. Updated about 11 years ago.

Status:
Closed
Priority:
Normal
Category:
Issues planning
Target version:
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:
Fixed
Affected version:

Description

Hi there,

this patch corrects a bug in the calculation of the done_ratio value in some edge case.

Ways to reproduce this bug:
  • Define a parent issue
  • Define two subissues on this parent issue
  • Set on one subissue estimated_hours to 0
  • Close subissue with no estimated_hours -> parent issue has done_ratio = 50%
  • Close subissue with estimated_hours set to zero value -> parent issue still has done_ratio = 50%

This patch solves this issue.

@Jean-Philippe: Maybe you or Toshi could take a look at this?

Best regards,
Daniel