Project

General

Profile

Actions

Feature #30464

closed

Show estimated hours on the overview page as well as spent hours

Added by Go MAEDA almost 6 years ago. Updated almost 6 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Category:
Time tracking
Target version:
Start date:
Due date:
% Done:

0%

Estimated time:
Resolution:
Fixed

Description

Currently, you can see total spent hours on the project overview page.

I think it is useful for project managers if total estimated hours are shown as well.


Files

Actions #1

Updated by Anonymous almost 6 years ago

+1, yes please!

Actions #2

Updated by Bernhard Rohloff almost 6 years ago

+1 Yes, could be useful.
I would also be great to have this information in a nice bar chart. But this is a future topic. ;-)

Actions #3

Updated by Go MAEDA almost 6 years ago

Added a test to the previous patch. The updated fixture issues.yml is identical to the one in the patch #30474.

Actions #4

Updated by Go MAEDA almost 6 years ago

  • Target version set to 4.1.0

Setting the target version to 4.1.0.

Actions #5

Updated by Marius BÄ‚LTEANU almost 6 years ago

I think we should show first estimated hours and spent time after (it is more natural).

Actions #6

Updated by Go MAEDA almost 6 years ago

Marius BALTEANU wrote:

I think we should show first estimated hours and spent time after (it is more natural).

Thanks, probably you are right.

Although I prefer to show spent time first, I found that VersionsController#show shows estimated time first. I think I have to update my patch for consistency.

Actions #7

Updated by Go MAEDA almost 6 years ago

Marius BALTEANU wrote:

I think we should show first estimated hours and spent time after (it is more natural).

Updated the patch. The new patch switched the position of spent time and estimated time.

Actions #8

Updated by Go MAEDA almost 6 years ago

  • Status changed from New to Closed
  • Assignee set to Go MAEDA
  • Resolution set to Fixed

Committed.

Actions

Also available in: Atom PDF