Feature #4488
closedRelated feature
0%
Description
Hi,
I've been using Redmine for a few days. I've evaluated other opensource PM products. This is by far the best so far in terms of balance between features and usability. Thanks a ton for the product!
I have a request - is it possible to create the following relation 'issue #101 starts x days after the start of issue #100' in 0.8.7?
It would be nice to have the following functionality while relating issues,- issue#100 precedes issue#101 by exactly x days
(issue #101 starts exactly x days after the end of issue #100)
This would automatically move the start date of #101 forward or backward depending on the end date of #100 - issue#100 precedes issue#101 by x days
(issue #101 starts atleast x days after the end of issue #100)
already implemented - issue #101 starts exactly x days after the start of issue #100
- issue #101 starts atleast x days after the start of issue #100
Pardon my ignorance if these features have been addressed in other issues. I did take a look at the Subtasking issue #443, but was hoping for an integrated feature, instead of a plugin.
Updated by ga work almost 15 years ago
- Assignee changed from Jean-Philippe Lang to Mischa The Evil
Updated by Mischa The Evil almost 15 years ago
ga work wrote:
- Assigned to changed from Jean-Philippe Lang to Mischa The Evil
Have you assigned this issue to me with a specific reason?
ga work wrote:
Pardon my ignorance if these features have been addressed in other issues
Not that I know of currently, but it might be possible that I've missed one... If I find one I'll relate it nonetheless :)
Updated by ga work almost 15 years ago
I thought Jean might be unavailable since there was no comment, so I assigned it to you.
Thanks for the reply!
Updated by Felix Schäfer over 14 years ago
- Status changed from New to Closed
- Assignee deleted (
Mischa The Evil)
The "precedes/follows" relations are part of the relations that are available in since 0.9, I think this fixes this request.