Hi,

I've been using Redmine for a few days. I've evaluated other opensource PM products. This is by far the best so far in terms of balance between features and usability. Thanks a ton for the product!

I have a request - is it possible to create the following relation 'issue #101 starts x days after the start of issue #100' in 0.8.7?

It would be nice to have the following functionality while relating issues,
  • issue#100 precedes issue#101 by exactly x days
    (issue #101 starts exactly x days after the end of issue #100)
    This would automatically move the start date of #101 forward or backward depending on the end date of #100
  • issue#100 precedes issue#101 by x days
    (issue #101 starts atleast x days after the end of issue #100)
    already implemented
  • issue #101 starts exactly x days after the start of issue #100
  • issue #101 starts atleast x days after the start of issue #100

Pardon my ignorance if these features have been addressed in other issues. I did take a look at the Subtasking issue #443, but was hoping for an integrated feature, instead of a plugin.