Project

General

Profile

Actions

Defect #9429

closed

Percentage Done of Subtasks of Subtask are not updated

Added by James Ang over 12 years ago. Updated over 12 years ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Issues
Target version:
-
Start date:
2011-10-17
Due date:
% Done:

100%

Estimated time:
Resolution:
Invalid
Affected version:

Description

Hi,

I'm using Redmine 1.2.1 and I noticed that the "% Done" for Level 3 subtasks of subtask are not updated accordingly even when it's closed (empty bar with 0%). But the "% Done" for the 2nd-level are updated correctly.

Can some verify if this is happening not only to mine setup.

Task #1 <- progress bar updated correctly (I presumed)
- Subtask #2 <- progress bar updated correctly based on its subtasks
- - Subtask #3 <- progress bar not updated
- - Subtask #4 < progress bar not updated
- Subtask #5 <- progress bar updated correctly based on its subtasks
- - Subtask #6 <- progress bar not updated
- - Subtask #7 < progress bar not updated

The "% Done" bar in the "Issue" page is no longer shown for selection during updating.

Thanks.
James

Actions

Also available in: Atom PDF