Time tracking code should respect weekends as "no work" days

Added by Matthew W over 15 years ago. Updated over 11 years ago.

Status:
Closed
Priority:
Normal
Category:
Issues
Target version:
Start date:
2008-11-11
Due date:
% Done:

0%

Estimated time:
Resolution:
Fixed

Description

I imagine this is a common requirement for a lot of companies - we don't work at weekends! (at least, by default we don't work at weekends).

It would be nice if the Gantt chart, the calendar, and the code which sets start and due dates on the basis of issue dependencies etc, treated weekend days by default as "non-work" days.

I imagine this would have implications along these lines (Forgive me any mis-assumptions as I'm not 100% clear on how your time-tracking logic works at present):

- Issues are never automatically scheduled for weekend start dates
- Weekend days during the time scheduled for a ticket, are not counted towards the length of time spent on that ticket
- This would mean that (amongst other things), when an issue is pushed back so that it spans a weekend, the due date is pushed back by an additional 2 days to account for the fact that no actual work will take place over that weekend
- Any logic which exists to fill out due dates on the basis of estimates, should not by default count weekend days towards time spent