Description

When I have issue A and issue B, and I assign issue B to follow issue A I want to still be able to schedule the start date for both A and B on the same day.

Currently if I schedule issue A and issue B to start on the same day, than I say issue B follows issue A, issue B's start date is changed to the next day after issue A's due date. Issue A may only take an hour which means issue A and issue B could technically start on the same day.

Instead of moving the B date out a day after the due date of A, set the start date of B to the due date of A and then let me change the start date of B if it needs to be the next day.


Files

seq_issues_start_end_same_day.patch (534 Bytes) seq_issues_start_end_same_day.patch Patch of the fix in comment 1 against r3940 Brian DeVries, 2010-08-17 10:23

Related issues

Has duplicate Redmine - Feature #6127: Preceeded by / followed by - Same dayClosed2010-08-13

Actions
Is duplicate of Redmine - Patch #3195: issue's start date could be the latest due date of predecessorsNew2009-04-17